HomeTopicsBusinessA year after work starts, little sign of Nicaragua canal

A year after work starts, little sign of Nicaragua canal

RIVAS, Nicaragua — A year ago, to much fanfare, a Chinese consortium planning on building a canal across Nicaragua to rival the century-old one in neighboring Panama started initial work with a target completion date of 2020.

Today, however, there is no further sign of progress beyond the dirt paths the Hong Kong Nicaragua Development Group carved out near the mouth of the Brito River, meant to be the Pacific Ocean gateway to the $50-billion canal.

HKND has admitted work had been delayed, with excavation pushed off to the end of next year. It blamed the lateness of an environmental study which was approved by authorities in November.

In the town of Rivas, located near the opening of the Brito River, unease and anxiety has taken hold.

Recommended: Financial, environmental questions plague Nicaragua canal project

Although the government has promised its 200,000 inhabitants the canal would bring them lasting prosperity, rural folk on the outskirts fear only they will be uprooted to make way for the massive project.

“If the canal comes, where will we be settled?” asked Ruth Campos, a resident in her 60s in the town of Las Lajas.

Residents uprooted

She is one of 27,000 Nicaraguans who are to be relocated because of the construction of the canal which aims to accept passage of 3,500 cargo ships a year, according to HKND.

The consortium was given a concession in 2013 to build and run the Nicaragua canal for 50 years, renewable for another half century.

The design for the manmade waterway calls for a canal 278 kilometers (173 miles) long, 280 meters (919 feet) wide, and 30 meters (98 feet) deep.

Its goal is to capture five percent of global maritime traffic, especially superfreighters going between America and Asia whose size prevents them using the Panama canal.

“They can kill me, but I’m not leaving,” warned a 95-year-old resident, Cristina Lopez, whose town of La Virgen is to be bulldozed to make way for the canal according to HKND’s maps.

“This is where I was born, and it’s where I will die,” she said.

Related: Nicaragua Canal project surrounded by air of intimidation, opponents say

A neighbor, Esperanza, 70, said: “Here there will be some deaths because nobody wants to leave their home. How can these people come to force us from our land?”

Nicaragua canal path
Inti Ocon/AFP

Environmental fears

The locals, and environmental groups, fear the massive project will destroy Lake Nicaragua, a vast inland body of fresh water that is Central America’s biggest, and a key thoroughpoint for the canal.

HKND plans to build a logistics center for the canal in Rivas.

In September, work was meant to have been completed on a first stage that would see five million tons of earth excavated. But the delay attributed to the environmental impact study has pushed that back.

The work “may be delayed, may change some plans,” Eden Pastora, a member of the government’s Great Interoceanic Canal Commission told AFP.

“But the project will go on,” he said.

Many doubts

HKND, still in what it calls the “conception phase” of the project, is to start building a port early next year on Nicaragua’s Caribbean coast, in Punta Gorda, to bring in the heavy machinery needed for the next stage.

The Australian head of the project for the HKND, Bill Wild, said late last month that work was “behind schedule” by nearly a year.

He said late approval of the environmental impact study was to blame.

That study, carried out for HKND by a British firm, Environmental Resources Management, concluded that the canal would have “significant” consequences, especially for Lake Nicaragua. Parts of the canal are also to be built on earthquake-prone terrain, it noted.

But it stated that, if executed correctly, the canal would have a “positive” impact for the country.

Read also: Will the Nicaragua Canal ruin the ‘Galapagos of Central America’?

A hydrology expert, Salvador Montenegro, highlighted the problem of opening up Lake Nicaragua, whose shallow waters lie above an ancient tectonic zone of seismic and volcanic activity.

An Asian affairs analyst, Alberto Aleman, said HKND has left open “many questions about the environmental aspects” of the project.

“Apparently not enough capital, not enough investment has been raised, and they have not been able to come up with a study able to dispel all the doubts,” he told AFP.

Trending Now

Costa Rica Biologists Identify New Insect Species in Museum Collections

Biologists at the University of Costa Rica have uncovered 16 new species of leafhoppers after examining insect collections that sat untouched in museums for...

Costa Rica Probes Osa Permits in Fila Costeña Amid Eco Concerns

Costa Rica's Comptroller General of the Republic (CGR) has accepted a complaint and sent it to its oversight unit for review. The focus is...

Costa Rica’s President Attacks Opponents After He keeps His Immunity

Costa Rica’s President Rodrigo Chaves lashed out at opposition lawmakers after Congress rejected a request to strip him of immunity, a step that could...

Lowest Hotel Occupancy Outlook in Costa Rica Since 2022

Hotels across the country project an average occupancy rate of 77% for the end of 2025 and the beginning of 2026, based on a...

Costa Rica Picnic Festival 2026 Lineup Headlined by Christina Aguilera, Maná and Nodal

Picnic Festival organizers revealed the lineup for the 2026 edition yesterday, setting the stage for two days of live music at Centro de Eventos...

How Costa Rica’s 2026 Tax Changes Benefit Digital Nomads and Expats

Independent workers across Costa Rica will soon have a simpler way to handle their income taxes. Starting January 1, 2026, a reform to the...
Costa Rica Coffee Maker Chorreador
Costa Rica Coffee Maker Chorreador
Costa Rica Travel Insurance
Costa Rica Travel

Latest News from Costa Rica