HomeTopicsExpat LivingWater Upgrades for Jacó, Quepos and Manuel Antonio Stall After Seven Years

Water Upgrades for Jacó, Quepos and Manuel Antonio Stall After Seven Years

A loan-funded program to upgrade water systems in Jacó, Quepos, Manuel Antonio, Limón and Guácimo has reached just 25% completion after seven years, according to a Ministry of Finance report on externally financed public projects. The program is one of five projects the ministry singled out in its review of the first half of 2026. They have been in execution for between seven and nearly 12 years, and several will not meet their current deadlines.

The delays carry a direct cost as Costa Rica has paid $43.7 million in commitment fees, the charges lenders apply to approved loan money that has not yet been disbursed, according to the report. The Coastal Cities Water and Sewer Program, run by the Costa Rican Institute of Aqueducts and Sewers (AyA) with financing from the Central American Bank for Economic Integration (BCIE), was designed to last six years. A 38-month extension pushed its end date to June 2029.

Its six components include upgrades and expansions of the water systems in the five towns and a new building for the National Water Laboratory. The ministry attributed the delays to recurring problems with contracting, design approvals and expropriations. The longest-running project on the list is the Transportation Infrastructure Program of the Ministry of Public Works and Transport (MOPT), financed by a $450 million loan from the Inter-American Development Bank (IDB). It has been in execution for 11.6 years.

By the end of June, $439.83 million of the loan had been committed and $348 million disbursed. The current disbursement deadline is November 2026 under a third extension, and the ministry expects a fourth. The program’s goals hinge on the new highway to San Carlos, where work stalled for six years after the original construction contract was terminated. Work resumed last year on the southern section, which is just over 15% complete, in a sector where Costa Rica’s highway projects have repeatedly run over budget and behind schedule.

MOPT will finance the central section with its own funds after the IDB declined to approve the only bidder. Public Works Minister Efraím Zeledón told the Legislative Assembly’s Treasury Affairs Committee that 17 properties in the central section and four in the southern section still have to be acquired, though he said those parcels are not needed to complete the highway’s main trunk.

Two other AyA projects also made the list. A program to reduce non-revenue water, meaning water that is produced but never billed because of leaks, illegal connections or metering errors, has been underway for 10.8 years and stands at 66% progress, with about $50 million of a $130 million plan executed.

The report cited low bidder participation, tenders declared void, limited capacity to manage several contracts at once and high turnover among specialized staff. AyA President Lourdes Saúrez said in August that the project had accelerated considerably, adding that non-revenue water had fallen four percentage points to about 49% of production and that the target once the work is finished is 38%.

A separate AyA program to expand water supply in the San José metropolitan area, along with urban aqueducts and the Juanito Mora sanitary sewer system, is 55% complete after 8.1 years. Of its 11 works, divided into 18 stages, 10 are finished, three are under construction and five remain in tendering or technical preparation.

The ministry downgraded that program’s condition to critical. It concluded that even a 42-month extension, which moved the disbursement deadline to Oct. 30, 2027, would not give it enough time. The fifth project is the Costa Rican Electricity Institute’s (ICE) Borinquen I geothermal plant near Liberia, Guanacaste, financed by the Japan International Cooperation Agency (JICA). It was originally due for completion in September 2026 and is just over 56% complete after nine years.

As of June, ICE was seeking an extension of at least four years on the loan, and the institute has said the plant will be finished in early 2030. The ministry described the project’s progress as limited. Of the $43.7 million in commitment fees, $23 million went to the IDB, with 67% of that amount tied to the transportation program. Fees to the BCIE totaled $13.5 million across several institutions, and delays at Borinquen I have cost $4.6 million in fees to JICA.

The ministry said disbursement extensions are legitimate tools for managing delays but should be exceptional and technically and financially justified, and should not become a recurring practice. The findings arrive as a national El Niño plan warns of major risks to water supply in the months ahead. MOPT, AyA and ICE had not publicly explained the causes of the delays or the status of their extension requests as of Friday.

Trending Now

El Niño Is Already Cutting Costa Rica’s Coffee Harvest by Up to 15%

Costa Rica's coffee growers now expect a harvest 10% to 15% smaller than first estimated as El Niño's irregular rains and rising heat reach...

Costa Rica’s Native Stingless Bees at Center of Supreme Court Fight

Costa Rica's tiny native bees have become the center of a legal battle that could affect beekeepers, honey producers and efforts to protect some...

Nearly Two Thousand Chinese Businesses Established in Nicaragua Since Free Trade Agreement Took Effect

Nearly 2,000 Chinese businesses have been established in Nicaragua during the first two years of the free trade agreement with China, according to the...

Tamarindo Celebrates Halloween Weekend With Costume Surfing, Parades and Beach Parties

Tamarindo is getting ready for a Halloween weekend that promises everything from surfers riding waves in costumes to trick-or-treating, costume contests, live music and...

Scarlet Macaws Start Nesting in Costa Rica, and You Can Watch Live

Scarlet macaws are pairing off on Costa Rica's Pacific coast. Watch 11 live nest cams, with first chicks due by January.

Flying to the US Soon? Every Passenger Must Sign a New Form From Nov. 3

Every passenger flying to the US from Nov. 3, even on a connection, must sign an Ebola form or be denied boarding.

Two of Every Three Dairy Imports in Costa Rica Now Come From the US

Costa Rica imported $66.4 million in dairy products from the United States in the first eight months of 2026, nearly four times the $17.5...

Costa Rica’s Cambronero Bridge to Reopen

The Cambronero bridge on Route 1 is scheduled to reopen Tuesday, November 3, restoring traffic through a stretch of the Inter-American Highway closed since...

Costa Rica Hospitals Overwhelmed as Patients Wait Up to Eight Days for Treatment

Patients at several of Costa Rica's largest public hospitals are waiting as long as eight days for a hospital bed, with overcrowded emergency departments...
Loading…

Latest News from Costa Rica

Costa Rica Coffee Maker Chorreador
Costa Rica Car Rentals
Costa Rica Travel Insurance
Costa Rica Travel