Panama Canal claims $737 million in cost overruns

PANAMA CITY – The consortium expanding the Panama Canal is making fresh claims for cost overruns totaling $737 million, officials said Friday.

Canal administrator Jorge Quijano told reporters that the Panama Canal Authority had received two claims on Tuesday that “will be evaluated” to determine if there is probable cause.

But he warned that “at first glance, the issues will be very difficult for the counterparty to justify.”

And in the latest setback for the behind-schedule, over-budget upgrade, a union representative said excavation work was on hold after negotiations broke down between the consortium and workers who have been on strike since Tuesday.

About 1,000 workers are on strike, demanding better safety and treatment. Talks between the two sides are due to resume Monday.

One of the consortium’s latest claims, for $333 million, is related to the weight of the gate for the third set of locks it is building for the canal — at 55,000 tons, compared to the 35,000 tons initially planned.

But Quijano pointed to a clause in the contract according to which the canal authority would pay up to the value of a gate weighing 49,000 tons.

The second claim, for $404 million, is due to delays in the fourth phase of excavation in the Pacific sector.

The consortium, Grupos Unidos por el Canal, says that the delay in excavation work may mean it will not receive water needed to test the gates.

Quijano, however, said he has a “Plan B” to provide the necessary water for testing.

The canal authority will pay another $120 million in adjustments to the contract and other small claims, Quijano said.

Work began in 2007 to expand the canal with a third set of locks to enable it to handle the modern mega-freighters that global shipping companies prefer.

But the $5.25 billion project has been plagued by delays, strikes and a bitter dispute over $1.6 billion in cost overruns with the consortium carrying out the upgrade, led by Spanish construction firm Sacyr.

Initially scheduled for completion in 2014, the project’s due date has been pushed back to early 2016.

Nearby Nicaragua, meanwhile, launched construction this week on a rival canal, a $50 billion project that the Chinese firm behind it plans to complete in five years.

Quijano estimated that the Nicaragua Canal construction would reduce by up to 30 percent the transit of ships through the Panama Canal, because it is closer to the lucrative market in the United States.

Trending Now

Guards Find Sharpened Spoons as Costa Rica’s Megaprison Tops 600 Inmates

Costa Rica's new maximum-security prison held more than 600 inmates by Tuesday, eight days after the first transfers. Guards there have already found weapons...

Costa Rica Uses Smartphones to Create 3D Maps of Pacific Coral Reefs

A Costa Rican conservation organization is using ordinary smartphones to create detailed three-dimensional maps of coral reefs along the country's Pacific coast, giving researchers...

Forbes Picks Costa Rica’s Rancho Pacifico to Beat the Crowds

A Forbes feature names Rancho Pacifico, a 20-guest rainforest resort above Uvita, among its top shoulder-season escapes from the crowds.

Red Tide Spreads in Costa Rica’s Gulf of Nicoya and Cooking Won’t Make Shellfish Safe

SENASA widened the Gulf of Nicoya red tide ban. Cooking doesn't make oysters, mussels or pianguas safe.

Cristiano Ronaldo Announces Portugal Retirement at 41

Portuguese football legend Cristiano Ronaldo announced on Thursday he was retiring from international football at the age of 41. Ronaldo made his debut for...

El Refugio Costa Ballena: Making a Difference for Animals and the Community

From rescuing animals in need to providing affordable spay/neuter surgeries and supporting community members’ loving pets, one local nonprofit is changing the lives of...

Pope Leo XIV Departs for First Latin America Journey to Uruguay Argentina and Peru

Pope Leo XIV leaves Rome on Friday, November 6, 2026, for a twelve-day apostolic journey to Uruguay, Argentina and Peru. The Holy See Press...

Two Bull Sharks Found Dead in a Guanacaste Estuary They Had Never Been Known to Enter

Two bull sharks, rays and fish were found dead in a sand-blocked estuary at Playa Langosta near Tamarindo. Environmental authorities are investigating the cause.

Your 2027 Marchamo Is Due and the New Sticker Can Only Go On Once

The 2027 marchamo is due by Dec. 31, with a new 10-year sticker you can only stick on once.
Loading…

Latest News from Costa Rica

Costa Rica Coffee Maker Chorreador
Costa Rica Car Rentals
Costa Rica Travel Insurance
Costa Rica Travel