Guanacaste Power Co. Announces Outages

September 26, 2008

In the face of too much demand, Coopeguanacaste, the electrical cooperative in the northwestern province of Guanacaste, on Thursday began a new wave of six-hour electrical outages in El Coco and Ocotal from 8 a.m. to 2 p.m. on Thursday.

Other interruptions will occur during the same hours on Oct. 2, 9, 16 and 24. Previously, most outages lasted four hours, but in a memo addressed to Coopeguanacaste’s clients, operations manager

Eduardo Cabalceta explained workers needed larger blocks of time to improve the infrastructure.

Electrical consumption in the Santa Cruz and Carrillo cantons has increased by 15 percent in the last three years.

 

You may be interested

Costa Rica considers upgrades to Limón cruise terminal, marina
Costa Rica
3085 views
Costa Rica
3085 views

Costa Rica considers upgrades to Limón cruise terminal, marina

Alejandro Zúñiga - May 7, 2021

The Atlantic Port Authority's (JAPDEVA) has contracted U.S.-based Moffatt & Nichol to conduct feasibility studies regarding a new cruise terminal…

Former Latin American leaders condemn ‘breakdown in the rule of law’ in El Salvador
El Salvador
8 views
El Salvador
8 views

Former Latin American leaders condemn ‘breakdown in the rule of law’ in El Salvador

The Tico Times - May 6, 2021

Some 20 former presidents of Spain and Latin America, including Felipe Calderón and Vicente Fox from Mexico, and Álvaro Uribe…

Quepos airport renovations (finally) underway
Costa Rica
11 views
Costa Rica
11 views

Quepos airport renovations (finally) underway

Alejandro Zúñiga - May 6, 2021

Renovation and expansion of the runway at La Managua Airport in Quepos began Wednesday and will completed before September. "The…