HomeArchivePublic Works Plans May Shift to High Gear

Public Works Plans May Shift to High Gear

Troubled by shoddy roads and crumbling bridges, lawmakers have passed a bill to promote awarding public works projects to private companies.

But some experts say the bill, which was approved last week and awaits the president’s signature, will do little to mend Costa Rica’s backlog of public works projects unless the state demonstrates a greater commitment to the projects.

Since lawmakers 14 years ago gave the state permission to grant concessions for projects to private firms, not a single project has been completed under such an arrangement.

Meanwhile, the state lacks the money and expertise to build the highways, railroads and bridges that the country desperately needs.

Costa Rica’s highways have not kept pace with the country’s 24 percent population growth during the past 10 years. In a report last year, the Japanese International Cooperation Agency (JICA) stated that “most of the 1,330 bridges on national highways suffer from severe deteriorations” (TT, Aug. 10, 2007). The country’s roads are overloaded and poorly maintained, according to a report released in December by the University of Costa Rica.

“The country began to grow, and infrastructure stayed exactly the same,” said Claudio Donato, an expert in Costa Rican concessions law at the firm Zürcher, Odio & Raven. “That created a bottleneck that the state cannot solve by itself.”

Recognizing that the original concessions law of 1994 has not produced the desired results, lawmakers are hoping the bill will make contracts more attractive for both the state and the private sector. Donato is skeptical.

“Reforming a law, improving a law, is always a good thing,” he said. “But it’s a mistake to think these reforms will substantially change the way public works projects are executed in this country.”

Under the 1994 law, the state – or another interested party – can design an infrastructure project, ranging from an airport to a jail. After a public bidding process, the winning firm builds and operates the project, charging fees to users until it recuperates its investment. The entire concession can be held for up to 50 years, after which the project is taken over by the state.

Among its biggest changes, the bill will allow construction firms to bow out of the project once construction is complete, leaving partners with management expertise to operate it.

“That’s more attractive for firms,” Donato said.“More firms will participate (in the bidding process), which leads to more competition and better offers.”

Parts of the reform also will benefit the National Concessions Council (CNC), a technical body that helps the executive branch, municipalities and other state institutions grant concession projects. In past years, if the concessionaire bailed, CNC had to redo the entire public bidding process.

Now CNC can transfer the concession directly to the runner-up.

The bill also speeds the expropriation of land required for an infrastructure project.

Acquiring land has been a major obtstacle for previous concessions.

The changes are a step forward, said Guillermo Matamoros, CNC’s technical secretary.

Still, he worries that the reform puts stricter controls over CNC’s ability to hire outside consultants. That could weaken what he sees as an already underfunded and understaffed institution faced with a Herculean task, he said.

CNC’s budget for 2008 was ¢1.3 billion (roughly $2.5 million). The institution has a staff of 36, half of which serve administrative and auditor functions.

Despite being responsible for highly complex infrastructure projects, the council’s staff includes only four engineers, two of whom are consultants whose terms will expire in the coming months. Furthermore, the institution has no economists or finance experts, both crucial for these types of projects, Matamoros said.

Under the reformed law, before hiring a consultant, CNC must first try to find someone within the civil service who meets the required qualifications and then negotiate a transfer with that person and his employer.

With the intent of attracting higher-quality personnel by offering better salaries, the reform creates new pay categories within the civil service for employees with the qualifications CNC requires.

Matamoros said the reform should have exempted CNC from civil service hiring rules altogether. This would allow the council to hire and retain employees with the specialized knowledge needed to guide projects to completion and negotiate on a level playing field with representatives of private firms.

“An excellent training program serves no purpose if there isn’t an excellent compensation program that makes it possible to retain people,”Matamoros said. “That is the CNC’s main problem right now. Retaining qualified personnel … is how an organization can guarantee that lessons learned from previous experiences are put to use.”

These handicaps have slowed the CNC’s work: It takes the council about eight years to draft feasibility studies on a proposed project and organize a public bidding. By then, the studies may be outdated, Donato said.

Controversy and a skeptical public also tend to thwart concessions projects, Donato added.

“These projects have a bad reputation. People think private companies come to this country to become millionaires, destroy the environment, and take all the wealth,” he said.

Cowed by opposition and wary of accusations of corruption or favoritism, Donato said, public officials drag their feet on concessions.

fborges@ticotimes.net

ggillers@ticotimes.net

 

Hard Hat Areas

Caldera highway: Construction on a 77-kilometer highway connecting San José with the Pacific port of Caldera began in April after three decades of false starts. Autopistas del Sol, the consortium charged with building and operating the road for more than 25 years, is required to finish construction by July 2010.

San José-San Ramón highway: The expansion of the 68-km stretch of the

Inter-American Highway

connecting San José to the Pacific-slope town of San Ramón is stalled while CNC and Autopistas del Valle, the consortium charged with expanding and operating the highway for 25 years, renegotiate toll prices. The firm argues an increase in tolls is required to compensate for increased building costs.

CNC expects the negotiations to conclude soon and a change order to the contract submitted to the Comptroller General’s Office by July. If the modification is approved, construction could begin in a few months.

Liberia airport: The (extended) deadline for firms to issue bids for the construction and operation for 20 to 25 years of a new two-story, 13,500-square-meter terminal at DanielOduberInternationalAirport in Liberia, the capital of the northwestern province of Guanacaste, expires June 25.

Metropolitan Electric Train: Next week, CNC will re-submit to the comptroller’s office an updated version of a contract awarding a Brazilian firm permission to carry out the financial and environmental feasibility studies for a train connecting the four main Central Valley cities of San José, Heredia, Cartago and Alajuela. The comptroller rejected the original contract in April.

–Fabian Borges

Trending Now

Costa Rica Ranks Fifth in the World for Retirees in Global Relocation Index

Costa Rica ranks 20th out of 192 countries and territories in the 2026 Global Relocation Index, and fifth in the world for retirees, according...

Costa Rica’s CCSS Prioritizes Emergency Care on Strike Day

Costa Rica’s public health system has put backup plans in place for a nationwide strike called for today over problems with workers’ pay. Emergency...

Costa Rica Pauses School Rebuild Over Possible Archaeological Site

Costa Rica's National Museum sent an archaeologist to a rural high school in Pérez Zeledón yesterday after construction crews rebuilding the campus turned up...

Building in Costa Rica? Understanding Your Construction Contract Options

The final word in legal matters is in the hands of the Supreme Court. In Costa Rica the Supreme Court is composed of four...

Costa Rica Velodrome Shows Damage Less Than Two Weeks After Upgrade

Less than two weeks after reopening following more than ₡105 million (about $219,000) in repairs, the velodrome at Parque de La Paz in southern...

Costa Rican Influencer Julián Valverde Released by ICE Without Bond

Costa Rican content creator Julián Valverde was released from U.S. Immigration and Customs Enforcement custody in Florida on Sunday, Sept. 20, after five days...

Panama repeats China invitation to Canal Neutrality Treaty

Panama’s government again asked the People’s Republic of China to accede to the protocol of the Treaty Concerning the Permanent Neutrality and Operation of...

Saved by the Bell Star Mario Lopez Films Campaign in Costa Rica

Mario Lopez, the actor best known as A.C. Slater on the 1990s sitcom "Saved by the Bell," is in Costa Rica filming a campaign...

Jacó Beach Is Changing as New Residents and Major Brands Move In

For decades, Jacó’s economy has revolved around the beach. Surfing, hotels, restaurants, nightlife and weekend visitors from San José helped turn the Central Pacific...
Avatar
🌴 The Weekly Pura Vida

Costa Rica, Once a Week

The week's top stories, weather & insider tips — delivered every Sunday. One email, zero clutter.

🔒 Free. No spam. Unsubscribe anytime.

Loading…

Latest News from Costa Rica

Costa Rica Coffee Maker Chorreador
Costa Rica Car Rentals
Costa Rica Travel Insurance
Costa Rica Travel