HomeTopicsBusinessMoín cargo terminal will not be ready in January

Moín cargo terminal will not be ready in January

APM Terminals, the Dutch concessionaire currently building a container terminal in the Caribbean port of Moín, announced Friday that the $1 billion project will not begin operating as planned on Jan. 18, 2018, due to unexpected situations.

General Manager Kenneth Waugh in a news release said that APM has notified the National Concessions Council on that the company encountered unexpected, adverse situations “that force us to rethink the construction plan of the terminal.”

These problems relate to the surface compaction of the 40-hectare artificial island for the port, damage in the breakwater, and problems with the angles of 20 piles.

Waugh said that despite these issues with the project’s timetable, the company’s priority is to deliver a terminal that meets the highest standards of efficiency and quality capable of operating for 60 years, as established in the contract. Company engineers and other experts are evaluating possible solutions, he said.

APM Terminals said it will announce a new delivery date of the project in 30 days, and that the company will pay the fines for the delay. According to the contract, the company will have to pay $2,000 for each day of delay in construction and $2,000 more for each day that the terminal is not in operation.

The company stressed that despite the problems, there are aspects of construction on the 40-hectare island that are moving forward as expected, and that construction work is 73 percent complete.

Aerial view of the Moín terminal from December:

https://www.facebook.com/apmterminalsmoin/videos/1151109914938510/?permPage=1

More woes

The APM Terminals announcement comes just days after the government faced widespread criticism over an 80-meter (262-foot) error on a project to build a road connecting the Moín terminal with Route 32, the main road between the province of Limón and the Central Valley.

Public Works and Transport Minister Carlos Villalta appeared before the Legislative Assembly Committee on Public Expenditure Control on March 23 and said that the Ministry was aware that the project’s plans were wrong.

He said that when the public tender for the construction of the 2-kilometer (6,725 ft) road was published, the Transport Ministry did not have the environmental permits for the area where the road should connect with the Moín terminal; the environmental study had been performed on the wrong stretch of land.

While ministry officials were fully aware of the 80-meter difference, they decided to move forward “as it was the only way the cargo terminal could launch operations in January,” he said.

Legislators from five parties asked Villalta on Tuesday to step down his post. However, the Executive Branch backed the minister’s actions.

Presidency Minister Sergio Alfaro at a press conference later that day said that delaying the project represented additional costs: the fines that the government would be forced to pay the contractor for not complying with its part of the deal, which was building the road to the terminal.

“All decisions were taken to safeguard the country and avoid a cost that would be equal to the total value of the terminal,” Alfaro said.

He referred to the fact that if the government fails to finish the road before the terminal is ready, exporters and importers will lose a $20 rebate agreed on the transfer of each container on the terminal.

Alfaro estimated that losing that discount over the 30-year-period of the concession would represent roughly $1 billion.

Official data from the Foreign Trade Ministry state that 80 percent of Costa Rica’s exports pass through Limón.

Minister: “Road will be ready on time”

The contract for the 2.05-kilometer road was granted in a public bid to Consorcio del Atlántico, a corporation formed by local firm Constructora Meco S.A. and Spanish Puentes y Calzadas Infraestructuras.

The $72 million contract was awarded on June 30, despite the fact that MOPT officials were aware that the coordinates for the road were 80 meters off from the actual connection with the port.

The contractor subsequently charged $14 million to redesign the road and for additional works required to connect Route 32 to the terminal. The final cost of the road is expected to total $86 million.

Villalta, however, told lawmakers that the extra costs will consist of only $5.6 million, as officials had already allocated some $8.4 million for the extra stretch of road.

On Friday, the minister said in a news release that despite APM Terminals announcement, the government is maintaining its the deadline for the road’s completion.

“We will continue making all necessary efforts to build the interconnection road with the terminal in compliance with the contractual deadlines,” Villalta said.

Trending Now

Gusts Up to 80 km/h Hit Costa Rica’s Mountains as a Windy, Dry Week Begins

Gusts up to 80 km/h (50 mph) are forecast in Costa Rica's mountains and La Cruz as trade winds settle in for the week.

Costa Rica Can’t Build Its Way Out of Traffic, Public Works Minister Says

Costa Rica's public works minister says more lanes won't end traffic. Here's what MOPT is betting on instead.

Costa Rica Flights Caught in Only the Third Nationwide US Ground Stop Ever

The FAA stopped all US departures Friday. Here's what it means if you're flying to or from Costa Rica.

El Niño Could Leave 306,000 People in Costa Rica Short of Water

More than 306,000 people in Costa Rica could face problems getting drinking water as the strongest El Niño on record dries us out, according...

Santa Cruz, Home to Tamarindo, Leads Guanacaste in Murders and Car Break-Ins

Santa Cruz has 22 of Guanacaste's 75 homicides this year, with Tamarindo on top. OIJ detained 10, including two police officers.

Two Arrested in Killing of American Surfer Kurt Van Dyke in Costa Rica

Costa Rican investigators have arrested two people in the February killing of Kurt Van Dyke. He was the 66-year-old American surfer and Puerto Viejo...

Costa Rica Moves to Dock Pay for Education Workers Who Joined Strike

Costa Rica's government is moving to dock a day's pay from education workers who joined Wednesday's march against cuts to public education, after the...

Costa Rica Wildlife Cameras Catch Heron Catfish Hunts and an Ocelot Latrine

My camera traps continue to provide me with brief glimpses into the hidden lives of Costa Rica’s wild animals. Today we look at a...

Costa Rica Mourns Actor and TV Host Leonardo Perucci, Dead at 87

Leonardo Perucci, the Chilean-born actor and host of the 1980s TV hit Fantástico, died Tuesday at 87 after more than four decades on Costa Rican stages and screens.
L. Arias
L. Arias
Reporter | The Tico Times |
Loading…

Latest News from Costa Rica

Costa Rica Coffee Maker Chorreador
Costa Rica Car Rentals
Costa Rica Travel Insurance
Costa Rica Travel