Thermal Power Plant Had Problems Before Outages

A new thermal power plant in the Caribbean port of Moín had had multiple and serious mechanical failures long before last month’s countrywide blackout, the daily La Nación reported Monday.

The $44 million power plant had broken down 95 times since the Marubeni Corporation, a Japanese company, installed it in 2003. Between then and 2005, the plant was in full working condition only 30% of the time.

The plant, known as Moín III, broke down again in April when it sucked a metal fragment into one of its two turbines. The incident shut down the turbine and, along with other system failures throughout the country, sparked a nationwide blackout April 19 (TT, April 27).

The National Power and Light Company (CNFL), a subsidiary of the Costa Rican Electricity Institute (ICE), purchased the plant and leased it to ICE until this year, when the institute bought it.

According to La Nación, problems with the plant began in 2003, with everything from oil leaks to failures in purification equipment and emissions regulators. An ICE report blamed the repeated breakdowns on poor manufacturing, though the CNFL has returned to Marubeni a $5 million bond it had held as a quality guarantee.

For its part,Marubeni blamed the breakdowns on lack of maintenance and training, and stated that the equipment had been installed in good condition. ICE officials said they have billed the company $93,000 for repairs of the earlier breakdowns.

Last month’s turbine failure, however, caused extensive damage and is expected to cost more than $8 million to repair.

Meanwhile, a turbine in the nearby Moín II power plant that also failed around the same time is expected to cost another $4.5 million in repairs.

It will take at least until next year to get both turbines running.

In related news, ICE officials assured the public this week that the recent shutdown of the Cariblanco hydroelectric dam –which President Oscar Arias inaugurated earlier this month (TT, May 11) – is a routine part of bringing a new power plant on line and will not affect the country’s power supply. Cariblanco is still under guarantee, according to ICE, so the contractor must pay for the repairs, though there’s no word on when the 84-megawatt plant will be up and running again.

 

Trending Now

Five Costa Rica Regions on Yellow Alert as Saturday Rain Hits Soaked Ground

If you live in or are traveling through the Central Valley, the Pacific coast or the Northern Zone, you are now under a yellow...

Costa Rica Is One Vote From Co-Hosting the 2031 Women’s World Cup

Costa Rica is one step away from co-hosting the 2031 FIFA Women's World Cup, the biggest tournament in women's soccer. FIFA said Wednesday that...

Red Tide Spreads in Costa Rica’s Gulf of Nicoya and Cooking Won’t Make Shellfish Safe

SENASA widened the Gulf of Nicoya red tide ban. Cooking doesn't make oysters, mussels or pianguas safe.

Two Arrested in Killing of American Surfer Kurt Van Dyke in Costa Rica

Costa Rican investigators have arrested two people in the February killing of Kurt Van Dyke. He was the 66-year-old American surfer and Puerto Viejo...

Guided Hikes in Costa Rica Would Need ICT Licenses and Insurance Under New Bill

Companies that sell or lead guided hikes in Costa Rica would need a license from the Costa Rican Tourism Institute (ICT) and insurance covering...

Luisa Stefani Moves Closer to WTA Finals Semifinals After Dramatic Comeback

Brazil's Luisa Stefani and Canadian partner Gabriela Dabrowski moved closer to the WTA Finals doubles semifinals Wednesday after producing a dramatic comeback to defeat...

Costa Rica Can’t Build Its Way Out of Traffic, Public Works Minister Says

Costa Rica's public works minister says more lanes won't end traffic. Here's what MOPT is betting on instead.

Microsoft Global Outage Disrupts Outlook, Teams and Health Services Worldwide

Microsoft’s global outage ran into a second day Friday. Outlook email is still failing for many users, and parts of Teams, Copilot and other...

Monteverde Went From 25 Dry Days a Year to Nearly 120, BBC Reports

Costa Rica's best known cloud forest is in the international spotlight this week after the BBC published a lengthy feature on Monteverde, reporting that...
Loading…

Latest News from Costa Rica

Costa Rica Coffee Maker Chorreador
Costa Rica Car Rentals
Costa Rica Travel Insurance
Costa Rica Travel