HomeArchivePocosol Dam Project Controversy Continues

Pocosol Dam Project Controversy Continues

PRELIMINARY work on a hydroelectricdam project in the remote area ofPocosol, in the Northern Zone, was haltedafter the San Ramón MunicipalCouncil decided that the energy cooperativeConeléctricas, which manages theproject, must reevaluate the project’senvironmental impact.The dam would be the first constructedunder the Rural Cooperative EnergyProduction Law, signed by President AbelPacheco in early 2003. The President firstrefused to sign it and then agreed to, solong as a second bill was drafted to retractcertain aspects of the law, such as thosethat allow construction of dams in protectedareas (TT, Feb. 28, March 7, 2003).However, no such bill is in the worksThe Technical Secretariat (SETENA)of the Environment and Energy Ministryconfirmed for The Tico Times thatConeléctricas does not have an approvedenvironmental impact study to begin workon the project.ACCORDING to representatives ofthe Environment and Energy Ministry(MINAE) in San Ramón who visited thesite last week, if the cooperative continueswork it could permanently damage thearea’s ecosystem, which includes a delicateaquifer and numerous springs thatfeed the Peñas Blancas River.At least one member of SETENA saidthe project had not produced any significantenvironmental damage. According to localauthorities, Luis Fernando González ofSETENA inspected the project site withConeléctricas environmental coordinatorLuis Torres and determined that the negativeimpact on the environment was minimal.The inspection was conducted withoutthe presence of members of the municipalityof San Ramón, MINAE officials or representativesof the Monteverde ConservationLeague, which administers theChildren’s Eternal Rain Forest, a privatereserve adjacent to the site of the dam.THE municipality questioned Fernández’sassertion and sent its own representativesand personnel from MINAE toinspect the project. After that inspection,they ordered the roadwork stopped.Thus far, the cooperative has onlywidened pre-existing roads, according toofficials from Coneléctricas.It was not clear as of press timewhether widening the roads constituted“work” on the project.FÉLIX Villalobos, of the San RamónMINAE office, said the company’s activityhas destroyed some old-growth forest andcould be causing undue amounts of sedimentto be deposited in the Peñas BlancasRiver. He also said the company is workingdangerously close to several springs.“If they continue the work they’redoing, they’re going to provoke irreversibledamage,” Villalobos said.However, he said, most of the damagehas been limited to secondary forests.VILLALOBOS said he authored tworeports about the company’s work thatwere filed as official judicial complaintswith the San Carlos Prosecutor’s office,and a third is under way. He said thereports address the damage caused alongthree different one-kilometer stretches nearthe river that he claims puts the companyin violation of Article 33 of the Forest Law.Article 33 mandates that no constructioncan take place within 100 meters of springsor 15 meters of rivers in rural areas.Allan Artavia, head of the Municipalityof San Ramón’s Natural ResourcesOffice, said the company hasmade major earth movements and felledsome trees near the river.“It is a very fragile zone. We are veryworried,” Artavia said.The river, area residents say, hasalready suffered irreparable damage as aresult of other hydroelectric dams.Sediment-filled water released from thePeñas Blancas dam, run by the Costa RicanElectricity Institute (ICE), asphyxiatedthousands of fish in October of last year. InApril, some 500,000 kilograms ofmolasses spilled into the river after a tankat a sugar factory exploded, causing anothermassive fish kill (TT, April 30).“There aren’t rivers like there werebefore. The people can no longer use themfor fishing,” Artavia said. “There used to beplaces they could go with their families onthe weekends, but that’s no longer possible.”IN one case, the company may haveworked directly through private property.Longtime residents Robert and JaneKoutnik (parents of Tico Times editorAuriana Koutnik) own property in thearea, and claim that the company has bulldozed100 meters through their land toconstruct an access road.The Koutniks worked with the CostaRican Federation for the Conservation ofthe Environment (FECON) to file a formalcomplaint against the company regardingthe road, which they call illegal.Coneléctricas representatives did notrespond to a request for a response to theallegations by press time.CONELÉCTRICAS general managerCarlos Rodríguez said in a written statementthat the cooperative has received“important support” from the community,which has “motivated (the company) tomove forward with the project.”Rodríguez said the company has completedan environmental impact study andhas not started actual work on the dam project.He said he could not understand whyanyone would talk about “irreversible damage.”He mentioned that Coneléctricas purchased300 hectares in the area, only 10% ofwhich will be developed, and that the restwill be recuperated so that the area will bemore environmentally healthy than beforeconstruction of the three-meter dam.“OUR plan has always been to continuewith the procedures to construct theproject, giving maximum consideration tothe fact that the people who oppose it arefew, and the majority of them are not residentsof the area; what’s more, the advancementof the Environmental Impact Studyindicated positive results for its development,therefore we are not going to let theopportunity to construct the project escapeus,” Rodríguez wrote to The Tico Times.However, Artavia said the cooperative“didn’t come near the municipality beforestarting work.”“To this date, the company hasn’tbrought forth any information about thework they’ve done,” he said.

Trending Now

Your 2027 Marchamo Is Lower if You Drive a Private Car

If you drive a private car, your 2027 marchamo is probably a little cheaper than last year's. The National Insurance Institute (INS) puts the...

Nearly Two Thousand Chinese Businesses Established in Nicaragua Since Free Trade Agreement Took Effect

Nearly 2,000 Chinese businesses have been established in Nicaragua during the first two years of the free trade agreement with China, according to the...

Elena Rybakina Clinches Year-End World No. 1 Ranking After Tokyo Victory

Elena Rybakina has won the year-end World No. 1 ranking for the first time in her career, defeating fellow Kazakh Yulia Putintseva 6-2, 6-3...

Four Days of Rough Surf Ahead for Costa Rica’s Pacific Beaches

If you're planning on going to the Pacific coast this week, expect rough surf and storms every day. Waves could reach 2.7 meters (8.9...

Costa Rica Plans Blue Zone Seal and Wellness Tourism Push for Nicoya

Costa Rica plans an official Blue Zone seal and three Nicoya wellness tourism products by 2028, plus new care for centenarians.

High Tides Flood Homes in Costa Rica’s Puntarenas

High tides flooded homes in Puntarenas on Thursday, October 29, with authorities warning that elevated tides could continue along Costa Rica’s Pacific coast through...

Heading Out for Halloween in Costa Rica? Expect More Police on Patrol

Costa Rica police will patrol cemeteries, churches, bars and costume parties this Halloween weekend. Here's what to expect if you're heading out Oct. 31.

El Salvador’s Marcelo Arévalo Qualifies for ATP Finals Despite Vienna Upset

El Salvador’s Marcelo Arévalo and Croatian partner Mate Pavić have secured their place in the 2026 ATP Finals for the third consecutive year, although...

Costa Rica Now Has Its Own Wine Grape After a 50-Year Quest

Costa Rica now has a wine grape of its own. Peppevidor, a hybrid bred to grow in tropical heat, was certified as a new...
Loading…

Latest News from Costa Rica

Costa Rica Coffee Maker Chorreador
Costa Rica Car Rentals
Costa Rica Travel Insurance
Costa Rica Travel